European Growth Leaders 2026

Annual ranking data providerLSEG WorkspaceUsed with permission · acknowledgements

An independent research observatory tracking Europe’s listed growth companies.

Francesco Castellaneta, Full Professor of Strategy and Entrepreneurship, SKEMA Business School – Université Côte d’Azur (GREDEG) · Scientific Committee Diego Zunino and Jackie Krafft

← All companies

Annual rank9

Croatia · Industrials

Dalekovod

Designs and manufactures power infrastructure and has expanded from energy into transportation and information-and-communication technology.

+104%revenue growth
FY2022–FY2025
+1466%net-income growth
FY2022–FY2025
+268%stock return
FY2022–FY2025
+87%2026 stock return
current context only

Company profile

Grid engineering, specialist hardware and field delivery

Dalekovod is a Croatian engineering group that designs, manufactures and constructs electricity and transport infrastructure. Dalekovod-Projekt supplies engineering, Dalekovod OSO makes specialist overhead-line hardware, and Dalekovod d.d. delivers projects in the field. Its work ranges from 750 kV substations and long-distance transmission lines to railway electrification, with Norway and Sweden among its principal international markets.

Operating model

Design, hardware and construction sit in one group

Dalekovod-Projekt prepares power, transport, renewable-energy and communications designs; engineers use drones plus optical, thermal and laser cameras for surveys and condition analysis. Dalekovod OSO supplies line hardware, while the construction business carries projects through assembly, testing and commissioning.

Equipment and systems

From laboratory-tested fittings to 750 kV substations

At Velika Gorica, Dalekovod OSO develops and tests fittings and damping systems for overhead networks, with an accredited laboratory supporting product verification. Project references extend from the multi-voltage Plat substation in Croatia to the 750/330 kV Kijevska installation in Ukraine and a 390 km, 500 kV line designed, supplied and built with local subcontractors in Kazakhstan.

Projects in the field

Fjords, German corridors and a Croatian railway

On Norway's Vik-Sogndal line, crews are installing 50-metre towers for a fjord crossing in demanding wind and terrain. In Germany, the Landesbergen-Borken programme covers a 30 km section of 380/220/110 kV rehabilitation. The Dugo Selo-Križevci railway combines 35 km of reconstructed track, 35 km of new track and four stations.

Recent project momentum

Three project milestones now sit beside investment financing

By 30 July, Dalekovod had announced a selected €135 million German grid bid, four signed Swedish design contracts worth nearly €30 million and covering nearly 600 km of 400 kV lines, a corrected notice covering consortium contracts totaling €53.76 million for a 131.25 MW wind farm and its grid connection in North Macedonia, and access to up to €81.5 million for planned investment projects. Selection, signed contracts and financing access are different stages and are presented separately.

Current 2026 update

What is changing at Dalekovod in 2026?

Dalekovod is stretching across more of the grid-project lifecycle. A selected German bid would add long-dated field scope; Swedish contracts move the design arm upstream; North Macedonia combines wind construction with a 400 kV connection; and a new financing agreement provides access to investment funds.

Latest official evidence Project financing agreement Published 30 July 2026

The change in one sentence

Selection, design, construction and financing now appear side by side.

The four items sit at different stages and should not be collapsed into one pipeline figure. Germany is a selected offer, Sweden is signed design work, North Macedonia is signed consortium construction, and EUR 81.5 million is a financing-access ceiling whose drawdown and use are not disclosed.

Four lenses on 2026

The same four-quadrant format used in the Company profile.

01 · The German corridor

A selected offer would replace hardware across 45.4 km of double-circuit line

TenneT selected Dalekovod's offer for LOT1 of the 380 kV Ovenstädt-Eickum project after a tender. The scope is replacement of existing suspension and conductors on 45.4 km of double-circuit line between the two substations. Delivery is planned from 1 October 2026 to 30 September 2029 and the stated value is EUR 135 million. The release says selected offer; it does not say the contract was signed or work started.

  • Current signalSelected offer · EUR 135m · 45.4 km · planned 2026-2029
  • Why it mattersThe item would add three years of German field work, but selection, contract signature and commencement remain distinct milestones.
  • German grid selection Dalekovod · 2026-07-27

02 · Different ends of the lifecycle

Swedish design and Macedonian construction show two different group roles

Dalekovod-Projekt leads Tyréns on four Svenska kraftnät programmes worth nearly EUR 30 million and covering nearly 600 km of 400 kV lines, from feasibility and concept work through detailed design, construction support and as-built documents; documentation runs to 2034 and overall completion as late as 2038. In North Macedonia, a Dalekovod-KONČAR consortium signed contracts totaling EUR 53.76 million for 21 wind turbines with 131.25 MW capacity, a 400/35 kV substation and a double 400 kV line to MEPSO. Dalekovod's share is not disclosed.

  • Current signalNearly EUR 30m and 600 km of design · 21 turbines and a 400 kV grid link
  • Why it mattersThe design subsidiary participates upstream in project definition, while the consortium combines turbine, substation and grid-connection delivery; the consortium total is not Dalekovod-only revenue.
  • Swedish design contracts Dalekovod · 2026-03-19
  • North Macedonia contracts Dalekovod · 2026-06-30

03 · The investment capacity

Dalekovod joins a group financing agreement for planned investment projects

KONČAR Group signed a EUR 320 million project-financing agreement with EBRD, IFC, PBZ and ZABA. Dalekovod is included in the arrangement and can access up to EUR 81.5 million for planned investment projects. The release does not identify the projects, amount already drawn, timing, conditions or allocation between execution, equipment and other capacity.

  • Current signalAccess up to EUR 81.5m · use and drawdown undisclosed
  • Why it mattersFinancing capacity can support an investment programme, but access is not the same as investment completed, cash drawn or contract revenue.
  • Project financing Dalekovod · 2026-07-30

04 · What to watch

Three questions for the next disclosures

Three questions track conversion from announcement to executable work and investment.

  • German conversionDoes Dalekovod disclose contract signature and commencement of the Ovenstädt-Eickum scope on the planned timetable?
  • Project milestonesDo Swedish documentation milestones and North Macedonian construction commence and progress, and is Dalekovod's consortium share disclosed?
  • Financing useHow much of the EUR 81.5 million access is drawn, for which investment projects and on what timetable?

Annual record

Ranking history

Future editions add rows; they do not rewrite the 2026 record.

EditionMeasurement periodRankRevenue growthNet-income growthStock return
2026FY2022–FY20259+104%+1466%+268%